Mafenya Pipeline: Production goals exceeded!

Mafenya Pipeline: Production goals exceeded!

We are pleased to note that the Mafenya Pipeline team has achieved record productions.

They have completed 42.3km of the 43km pipeline.

This was achieved ahead of an already tight programme coupled with the fact that there were delays in the initial stages of the project.

Well done to the team!

Valve install at Mafenya

Valve Installation in Progress on Site